A Special Report on our Unfinished Pier

Burlington's unfinished pier

When negotiations to complete Burlington’s pier fell apart between the city and the contractor over a design dispute, the city called the contractor’s performance bond last January. In early July, lawyers for the city, the contractor, the bonding company, and the design engineer met to discuss the bonding company’s investigation into the dispute. One of the key points of discussion: whether a design dispute is covered under the terms of the bond. If the bond can’t be used, what are the costs and options to finish the pier?

To get to the heart of the dispute and possible solutions, I sat down for separate on-the-record interviews with Scott Stewart, the city’s general manager of community services; Tom Eichenbaum, the city’s director of engineering; Henry Schilthuis, president of Harm Schilthuis & Sons (pier contractor); and Doug Corby of Masters Insurance (an agent of Zurich, the contractor’s bonding company).

Click below to read my report.

Read More

The pier contractor isn’t bankrupt, and other rumours dispelled

Burlington's unfinished pier

We may never know whether poor design or poor construction techniques caused the delays in building Burlington’s pier. Even professional engineers disagree on that point. But maligning the contractor’s reputation and spreading false rumours does nothing to advance dialogue and understanding of the situation, nor find a productive solution. Below, some of the rumours I’ve heard (including from city officials!), and the reality.

Read More

City lacks transparency on pier costs, tax increases

The cost of Burlington’s unfinished pier is escalating, the “total budget” is a moving target and city documents contain contradictory and misleading information that masks the scale of the increases. Those are the findings of my recent investigation into the cost of the pier.

More than 130 of you have written to me to add your name to a list of residents seeking transparency from the city on costs and options to finish the pier, now two years behind schedule with no completion date in sight. City officials claim they can’t provide those answers for confidential legal reasons, and yet all this information is readily available in public documents – if you know where to look.

We can’t let the city shirk its duty to be accountable and transparent to residents any longer.

A week ago, city council unanimously approved in principle the recommendations of the citizen’s report, Shape Burlington, which called for more transparency, and early public involvement in decision-making.

There’s no time like the present. Councillors can put their words into action by coming clean on the costs and options to finish the pier.

Transparency on taxes

They can also explain why our city taxes have increased at triple the rate of inflation – about 6% per year for the last 10 years. But you won’t know that from reading city press releases, which downplay the increases. Those details are below.

Other issues

You’ll also find a summary of other issues in our city, including details of two public meetings on Freeman Station (May 16 and 18), the first meeting of the new waterfront advisory committee (May 14), and an opportunity to speak out on accident victims being charged for fire truck calls (June 1).

As always, communication here is two-way – leave a comment below, or email me at mariannemeedward@bell.net to comment or add your name to the list of residents seeking transparency on the pier.

Read More

Solution to finish pier exists – if City Hall will act

The pier in Burlington’s downtown waterfront has been plagued by delays and cost overruns. The question everyone is asking: what’s going on? We’ve been led to believe the contractor, Harm Schilthuis, is to blame. This is a local company with 57 years in business, which has successfully completed many other projects in Burlington, including the Discovery Centre and Aldershot Arena. Why would they stop work on a job if they didn’t have a reason?

Over the past few weeks, I’ve used my journalism background to investigate. There’s more to this story than we’ve been told. Furthermore, there’s an option on the table from the contractor to finish the pier – as early as this fall if work begins immediately. We know the longer this project is delayed, the more it will cost, and we’ll spend money on litigation, not finishing the pier.

Video of unfinished pier investigation

We need Burlington City Council to make a decision quickly – and tell taxpayers how much this is really going to cost. You can help by sending an email to mariannemeedward@bell.net to add your name to the list of residents asking for transparency on the options available to finish the pier, and the final price.

Details of my investigation are here, including interviews, research of public documents and material obtained under Freedom of Information. You can also leave a comment at the end of the post.

Read More